When an 18-storey building under construction collapsed in Eastleigh, Nairobi, on 23 October 2026, eight people died. Since then, Nairobi County officials have told the County Assembly that the building never received county approval and that the papers shown to the National Construction Authority (NCA) as county approval were forgeries. We covered the facts in Part 1 of this series.
Most people reading this are not putting up 18-storey towers. But the same weaknesses that officials described in Eastleigh, such as approvals nobody checked, professionals whose names were used without real involvement and floors added beyond what was applied for, also show up on bungalows, maisonettes and small rental blocks. This part turns the Eastleigh case into practical lessons you can use on your own project, whether you are building in Nairobi, Kisumu or from abroad.
Not sure whether your drawings and approvals are in order? Ask our team: WhatsApp 0789 217 685
This is Part 2 of a three-part series: Part 1: What happened / Part 2: Lessons / Part 3: How West Kenya Real Estate can help
Lesson 1: A stamped paper is not proof of approval
According to the Daily Nation, Nairobi’s Assistant Director for Development Control told MCAs that the approval documents presented for the Eastleigh building were forgeries. If a national regulator can be shown forged papers, so can a homeowner, a buyer or a bank.
What to do: confirm your approval with the county itself, not only through the person who handed you the document. Where your county has an online permitting system, check the application status there under your own login. Where it does not, visit the county planning office with your application reference and ask to see the approval on their records. Keep copies of every receipt, invoice and approval letter, and make sure the plot number on each document matches your title.
Lesson 2: Know the difference between change of use and building approval
Governor Johnson Sakaja said, as reported by Citizen Digital, that the Eastleigh plot had been granted a change of use, but the building plans had not been approved. These are different permissions. A change of use (or change of user) allows a different kind of development on the land, for example from a single dwelling to flats. It does not approve the architectural and structural drawings of the building you intend to put up.
What to do: ask exactly which approval each document represents. For most new homes and rentals you will need, at minimum, approved architectural and structural drawings from the county, NCA project registration and, where required, NEMA approval of the environmental assessment. Our sister guides on the building code requirements in Kenya and when you need an EIA report explain these steps in more detail.

Lesson 3: Your professionals must be registered and actually involved
In testimony reported by the Daily Nation, a registered architect told MCAs that his credentials were used through a broker for the Eastleigh change-of-user application, that he never met the developer and that he did not do due diligence. A professional stamp on a document means little if that professional is not designing and checking your building.
What to do:
- Meet your architect and structural engineer, and get their registration numbers in writing.
- Check architects with the Board of Registration of Architects and Quantity Surveyors (BORAQS) and engineers with the Engineers Board of Kenya.
- Agree in writing who will inspect the work on site and at which stages, especially foundations, columns, slabs and beams.
- Be wary of anyone who offers to “sort out” approvals for a fee without showing you the professionals behind the drawings.
Our guide on what a structural engineer does explains what you should expect from that role.
Lesson 4: Build what was approved, no more
County officials said the Eastleigh applications were for one basement and 15 levels, according to the Nation and Capital FM, yet the building rose to 18 storeys. The NCA has also told MPs that developers adding floors beyond their approvals is a recurring problem. Every floor adds load that the foundations, columns and beams were designed to carry, or not.
What to do: if you plan to add a floor later, have it designed into the structure and approved from the start. If you want to change the design during construction, go back to your architect and engineer and get revised approvals first. Our sister guide on approval for adding rooms or a floor covers this.
Lesson 5: Do not rely on the regulator to catch problems for you
NCA Acting Director General Susan Rutto told the National Assembly’s housing committee that the authority is present in only 27 counties, with 14 regional offices, and has no legal power to halt construction on its own, as reported by Citizen Digital. In Eastleigh, county enforcement notices reportedly did not stop the work. In many places, including much of Western Kenya, an inspector may never visit your site.
What to do: build your own quality control into the project. Budget for professional supervision, insist on concrete cube tests for structural concrete, check steel sizes against the structural drawings before every pour, and keep a photo record of each stage. If you live abroad, our guide on supervising construction remotely sets out a weekly routine.
Lesson 6: Buyers and tenants should check approvals too
If you are buying an apartment off-plan or renting in a new block, the Eastleigh case is a reason to ask for the building’s approval details and NCA registration before you pay. A developer with genuine approvals should have no difficulty showing them, and you can confirm them with the county. Once a building is complete, it should also have an occupation certificate.
A quick approvals checklist
- Title or lease checked, and the plot number matches every document.
- Architectural and structural drawings prepared by registered professionals you have met.
- County approval confirmed directly with the county, with receipts kept.
- NCA project registration in place, with the contractor registered in the right category.
- NEMA approval where your project needs it.
- Approved drawings kept on site and the building built to them, with no extra floors.
- Stage inspections by your engineer recorded, and an occupation certificate on completion.
Watch how a properly planned home goes from plan to finished house:
In Part 3 we explain how West Kenya Real Estate Ltd handles drawings, approvals and supervision for clients, so that each of these checks is part of the process from day one.
Read the full series
Need house plans and approvals you can trust?
Send us your plot location and what you plan to build, or the drawings and approval papers you already have. We will tell you what is in order and what is still needed.
Or call 0789 217 685 / 0724 481 087.