If you plan to build a house, apartment block or commercial building within Nairobi City County, you need county approval before any work starts on site. Building plan approval Nairobi applicants go through is more involved than many first-time developers expect: drawings must be prepared and signed by registered professionals, submitted through the county’s planning system, reviewed by a technical committee and paid for before a permit is issued.
This guide walks through the Nairobi process step by step, explains what the county looks for, and lists the common reasons plans are sent back. For drawings prepared to approval standard, our engineering and construction partner, Marble Engineering and Construction Ltd, offers architectural design and approval services from Marble Engineering, from concept to submission.
Need your plans approved in Nairobi? Ask about drawings and submission: WhatsApp 0789 217 685
Why building plan approval in Nairobi matters
Approval confirms that your building complies with zoning, land use, density, setbacks, structural safety and public health requirements. Without it, the county can stop the works, and you may struggle later with NCA project registration, bank financing, utility connections, occupation and resale. Approval is also your evidence that the design was checked by the authorities – an important protection after the building failures reported in recent years.
Development control in Kenya is governed by the Physical and Land Use Planning Act, 2019, which requires anyone developing land to obtain development permission from the county and sets statutory timelines for decisions and appeals. If you need a national overview, our earlier guide on house plan approval in Kenya covers county permits in general. This article focuses on Nairobi.
Documents you need before you apply
Gather these before submission. Missing items are among the most common reasons for delay:
- Copy of the title deed or lease, and current rates or land rent clearance where required.
- Owner’s written consent if the applicant is not the registered owner.
- Copy of the owner’s ID and KRA PIN.
- Architectural drawings – site plan, floor plans, sections and elevations – signed by a registered architect.
- Structural drawings and calculations signed by a registered structural engineer.
- Drainage and sewer/septic details, and other services layouts where required.
- Survey plan or registry index map showing the plot.
- Environmental (NEMA) documents for projects that require them, and other agency approvals where applicable.

The Nairobi county e-permit process step by step
Nairobi moved development applications online through its e-development permit (e-construction) system. According to Nairobi News, drawings and approval requests are submitted online, reviewed by the technical committee, and once they pass and the fee is paid, an approval permit is issued, with a QR code on approved plans replacing the old manual stamp. Because the county updates its systems from time to time, confirm the current submission channel with the county planning office or your architect.
- Engage registered professionals. Your architect and structural engineer prepare and sign the drawings and usually make the submission on your behalf.
- Check zoning first. Confirm what the zoning policy allows on your plot – use, height, plot coverage and setbacks – before detailed design.
- Prepare the submission pack. Drawings, calculations, ownership documents and any agency approvals, in the formats the portal requires.
- Submit on the Nairobi county e-permit system. Upload the documents and pay any submission charges invoiced by the system.
- Technical review. The county’s planning technical committee, which includes built-environment professionals, reviews the application and may request corrections.
- Pay approval fees. Once recommended for approval, the approval fee is invoiced and paid.
- Receive approved house plans. Download the approved drawings and permit, and keep copies on site.
- Register the project with NCA and notify the county at the inspection stages required during construction.
Architectural drawings approval: what reviewers check
| Area | What is checked | Typical issue |
|---|---|---|
| Zoning and land use | Use permitted on the plot, density, height | Proposed use or floors exceed zoning policy |
| Plot coverage and setbacks | Building footprint and distances to boundaries | Building too close to boundaries or road reserve |
| Parking and access | Parking bays, access roads, fire engine access | Too few parking bays for the number of units |
| Structural design | Signed calculations and drawings | Missing calculations or unsigned drawings |
| Drainage and sanitation | Sewer connection or septic design, stormwater | No clear disposal method shown |
| Fire and safety | Escape routes, staircases, fire provisions | Inadequate escape routes for multi-storey buildings |
Architectural drawings approval goes faster when the architect has already checked the design against these points before submission. Correcting a rejected plan and resubmitting usually costs more time than getting it right the first time.
Costs and how long approval takes
Nairobi approval fees are set by the county and are generally linked to the size and type of development, so they vary from project to project; they are invoiced through the system when you apply. Beyond county fees, budget for professional fees for design and engineering, and for any NEMA or other agency processes your project needs.
Timelines depend on how complete the application is, how many corrections are requested and how often the technical committee sits. Your architect can give you a realistic estimate for your project. Planning your programme around approval – rather than buying materials before you have a permit – avoids costly delays.
After approval: NCA registration and inspections
Approved drawings are not the end of the paperwork. Under the NCA project registration requirements, every construction project must be registered with the National Construction Authority, and the developer is responsible for applying within thirty days of awarding the contract. NCA lists approved architectural and structural drawings, county planning approvals, an NCA-registered contractor, and registered consultants among the requirements, and states that registration is currently free. Its FAQs indicate evaluation takes about seven working days after site due diligence.
During construction, keep approved plans on site and build exactly what was approved. Major changes generally require fresh approval. Working with a qualified structural engineer throughout the build helps ensure the structure matches the approved design.
Common mistakes that delay approval
- Starting site works before approval is granted.
- Using drawings that are not signed by registered professionals.
- Ignoring zoning limits on floors, coverage or use.
- Missing ownership documents or owner’s consent.
- Changing the design on site without amending the approval.
- Not budgeting for approval time when planning to build a house in phases.
Frequently asked questions
Can I start building while my plans are being approved?
No. Construction should only begin once you have approval. Starting early risks enforcement action by the county and problems with NCA registration and future transactions.
Do I need an architect for building plan approval in Nairobi?
Yes. Drawings must be prepared and signed by registered professionals, and the submission is normally handled by your architect, supported by a structural engineer.
How long are approved plans valid?
Development permission is valid for a limited period if work does not start, after which it may lapse or need extending. Check the conditions on your permit and the Physical and Land Use Planning Act, and ask your architect to confirm dates.
Get your plans ready for Nairobi approval
Our engineering and construction partner, Marble Engineering and Construction Ltd, prepares approval-ready drawings and handles submissions. Explore the architectural design and consultation services by Marble Engineering.
Or call 0789 217 685 / 0724 481 087.