The finishing stage of house construction in Kenya starts once the roof is on and the building is weather-tight, and it ends when you receive the keys. It is the stage most homeowners underestimate. The structure may look complete, yet plastering, ceilings, wiring, plumbing, tiles, doors, kitchen fittings, paint and external works still lie ahead, and this is where many projects stall or go far over budget.
This guide follows our stages of house construction in Kenya series, after the walling stage and the roofing stage. It sets out the right order of work, a checklist for each step and the mistakes that cost the most.
Reached the finishing stage and need a clear budget? Get a free cost estimate for your finishes from our quantity surveyor: WhatsApp 0789 217 685
Why finishes decide your final budget
Finishes are where specification choices add up. Integrum’s published construction cost rates for Kenya (updated 29 October 2026, indicative planning figures, not quotations) put a standard bungalow in Western and Nyanza at KSh 57,080 per m² and a luxurious bungalow at KSh 87,900 per m². The gap of KSh 30,820 per m² is mostly down to specification — the quality of tiles, ceilings, joinery, sanitary ware, fittings and external works. On a 110 m² three-bedroom bungalow, that difference is KSh 3,390,200. Decide your finish level before you start the house, not when the walls are up.
The right sequence for the finishing stage of house construction in Kenya
Doing finishes in the wrong order means breaking good work to fix something hidden behind it. The usual sequence is:
- First fix services — electrical conduits, switch and socket boxes, water and waste pipes, chased into walls and laid in floors.
- Internal plaster and external render — after first fix, so pipes and conduits are covered once.
- Floor screeds — levelled to the finished floor height you need for tiles or other floor finishes.
- Ceilings — gypsum, PVC or other ceiling boards, with openings for lights planned in advance.
- Windows and external doors — fitted and sealed so the house can be locked.
- Wall and floor tiling — wet areas first (bathrooms, kitchen), then living areas.
- Joinery — internal doors, kitchen cabinets, wardrobes and skirting.
- Second fix services — sockets, switches, light fittings, distribution board, taps, basins, toilets and showers.
- Painting — primer or sealer, undercoat and finish coats, with a final touch-up after second fix.
- External works — storm-water drains, septic tank or sewer connection, paving, walkways, fence and gate.
- Snagging, cleaning and handover.

Step-by-step checklist
1. Services (first fix)
- Mark every socket, switch, light point, TV and data point on the drawings before chasing walls.
- Pressure-test water pipes before they are covered.
- Check falls on waste pipes so water drains without blockages.
- Photograph every wall before plastering — you will need to know where pipes run later.
Wiring should be done by a qualified electrician, and the installation must pass inspection before Kenya Power connects supply. Our sister site explains what drives house wiring cost in Kenya.
2. Plaster, render and screeds
- Wet the walls before plastering and keep plaster damp while it cures to reduce cracking.
- Check walls with a straight edge; wavy plaster shows badly under paint and tiles.
- Fix corner beads on external corners for straight, durable edges.
- Set screed levels carefully at doorways so different floor finishes meet flush.
3. Ceilings
- Confirm the roof does not leak before boards go up — fix leaks first.
- Use a firm, level support frame; sagging ceilings are a common complaint.
- Leave an access hatch to reach the roof space and water tank connections.
4. Tiling
- Buy all tiles of one type from the same batch, plus a spare box for future repairs.
- Waterproof shower areas before tiling.
- Check falls to floor drains in bathrooms so water does not pond.
- Agree the tile layout (where cut tiles go) before work starts.
5. Joinery, kitchen and wardrobes
- Measure for kitchen cabinets and wardrobes after plaster and tiling, not from the drawings alone.
- Check doors close properly, with even gaps, and that locks and hinges are good quality.
- Seal timber that will be exposed to moisture.
6. Second fix and painting
- Test every socket, switch and light, and run every tap and flush every toilet.
- Apply the paint system the manufacturer specifies: sealer or primer, undercoat, then finish coats. Our guide to paint brands in Kenya compares common options.
- Use washable paint in kitchens, corridors and children’s rooms.
7. External works
- Lay storm-water drains so rain moves away from the foundations.
- Build the septic tank or soak pit to the approved design, or connect to the sewer where available.
- Budget for paving, the gate and the fence early — they are often forgotten until the money is gone.
Snagging and handover
Before you accept the house, walk through every room with the contractor and write a snag list: cracks, stains, uneven tiles, doors that stick, dripping taps, loose sockets, paint runs. Agree a date for each item to be fixed and keep any retention money until they are done. Ask for the as-built electrical and plumbing layout, warranties for fittings, and spare tiles and paint. Your contractor should also help you prepare for the occupation certificate. A construction site inspection by someone independent is worth the cost at this point.
Costly mistakes to avoid
- No finishes schedule. Without a written list of every tile, fitting and paint, quotes cannot be compared and costs creep up.
- Changing your mind mid-stage. Moving a socket after plaster or a toilet after tiling means breaking finished work.
- Plastering before first fix is complete. Chasing finished plaster leaves patches that show through paint.
- Buying the cheapest fittings. Taps, locks and hinges are used daily; cheap ones fail within months.
- Skipping waterproofing in showers and on flat roofs and balconies.
- Paying in full before snagging. Keep a retention until defects are fixed.
- Moving in before the house is complete, which makes the remaining work slower and messier.
Plan finishes from the drawings
The cheapest time to decide finishes is at the design stage, when the plan, BQ and finishes schedule are prepared together. A plan such as our luxurious 3-bedroom flat roof bungalow plan (WKRE045) shows how specification choices shape the final look. For the full budget picture, see our house construction costs in Kenya guide.
West Kenya Real Estate is registered with the National Construction Authority and delivers homes on a Design and Build basis, from drawings to handover. We can price your finishes, supply a finishes schedule or complete a house that has stalled at this stage.
Want the real cost of finishing YOUR house?
Send us your drawings or a few photos of the house as it stands, its location and the finish level you want. Our quantity surveyor will reply with a free indicative estimate and a clear list of what remains.
Or call 0789 217 685 / 0724 481 087.



